6530 Road Bridge Deck Replacement Progress Update

031820206530BridgeDeckReplacement

This past week the reinforced concrete bridge deck was poured. This was a major milestone for the project. Some major elements that remain include; painting existing bridge girders, bridge rail instillation, pouring sidewalk and approaches, sidewalk fence installation, site grading, asphalt paving, sign installation, asphalt painting.


The bridge is still on track to open in May, pending any workforce restrictions due to COVID-19, Though the bridge deck is poured, the construction area remains closed to vehicular and pedestrian traffic. 

Facebook Twitter Email

Other News in Moving Montrose Forward News

041320BridgeOpen_001

6530 Road Bridge OPEN

Posted on: April 20, 2020
03302020RiverbottomDrive

Riverbottom Drive Progress Update

Posted on: March 31, 2020
Detour Map

6530 Road Bridge Deck Replacement

Posted on: February 4, 2020

Otter Road

Posted on: October 24, 2019