6800 Waterline Replacement Project

Project Timeline


  • Design, Procurement, and Permitting: Complete August 2018
  • Project Award: October 2018
  • Construction Began: November 2019
  • Estimated Completion Date: May 2019

Project Team


  • Project Designer and Surveyor: Del-Mont Consultants (Montrose, CO)
  • Construction Contractor: Williams Construction (Norwood, CO)

Project Costs


  • Design: $35k
  • Construction: $640k (anticipated)
Project Overview
The City of Montrose’s recently-updated water master plan identified the construction of a dedicated fill line to the City’s Sunnyside Tank from the main Project 7 supply line in Highway 50 as a priority capital improvement.  To that end, the City constructed a new line between 6800 Road and the Sunnyside Tank in 2016. 

The City is now upsizing an existing 12-inch line between Miami and Sunnyside along the 6800 Road Alignment to 24-inch as shown in the attached Figure 1 (this project).  A future project (likely late 2019) will upsize the remainder of the line along Miami between 6800 Road and Highway 50.
6800 Road Waterline Project Area