6800 Waterline Replacement Project

Project Summary


  • Location: 6800 Alignment between Sunnyside and Miami Road
  • Designer: Del-Mont Consultants (Montrose, CO)
  • Contractor: Williams Construction (Norwood, CO)
  • Final Construction Cost: $635k
  • Completed: April 2019
Project Overview
The City of Montrose’s Water Master Plan identified the construction of a dedicated fill line to the City’s Sunnyside Tank from the main Project 7 supply line in Highway 50 as a priority capital improvement. To that end, the City constructed a new line between 6800 Road and the Sunnyside Tank in 2016. 

The City has upsized an existing 12-inch line between Miami and Sunnyside roads along the 6800 Road alignment to 24-inch as shown in the attached Figure 1 (this project). In 2020 the City will upsize the remainder of the line along Miami between 6800 Road and Highway 50.
6800 Road Waterline Project Area