Ogden Road Sidewalk Extension

Aerial view of project area with sidewalk design detailsProject Timeline

  • Notice of Award: Expected March 5, 2024
  • Estimated Completion Date: July 2024

Project Team

  • Project Designer: Del-Mont Consultants (Montrose, CO)
  • Construction Contractor: TBD

Project Costs

  • Design Cost: $25k (included full design of Ogden Widening to the Loutsenhizer Canal)
  • Construction Cost: TBD

Project Overview

In support of the Residences at Dry Cedar Creek affordable housing project currently being constructed immediately northeast of the Community Recreation Center, the city has partnered to construct a connecting pedestrian sidewalk along the southern side of Ogden Road between the Ogden/Woodgate Roundabout and the apartment complex. The project will include the relocation of some conflicting utilities, clearing of the area, construction of an embankment so the sidewalk will match the eventual widening of Ogden Road, and construction of the new sidewalk.