- Home
- Department Services
- Engineering
- Moving Montrose Forward
- Projects
- 2023 Contracted Street Maintenance Project
2023 Contracted Street Maintenance Project
Project Timeline
- Project Award: March 2023
- Estimated Completion Date: November 2023
Project Team
- Project Designer and Surveyor: City of Montrose Engineering Department
- Slurry/Cape Seal Contractor: TBD
- Overlay/Rebuild Contractor: TBD
Project Costs
- Design Cost: In-House
- Slurry/Cape Seal Contract: $1.4M
- Overlay/Rebuild Contract: $2.9M
- Other, Smaller Contacts (Sidewalk Repairs, Drainage Improvements, etc): $200k
Project Overview
The City of Montrose developed the Moving Montrose Forward (MoveMo) initiative, which places a renewed focus on street maintenance, reducing traffic congestion, and improving pedestrian and vehicular mobility throughout the community. As part of this effort, each year the city hires contractors to perform some of the larger-scale and specialized street maintenance construction. This contracted street maintenance work is in addition to typical routine maintenance activities performed by the city’s Streets Division.
Contracted street maintenance work generally includes surface treatments consisting of slurry and cape seals as well as more-robust pavement maintenance activities such as complete rebuilds and overlays. Areas to receive contracted pavement maintenance activities in 2023 are shown on the adjacent map.
Slurry seals are a combination of a fine aggregate and an asphaltic binder that work to smooth out surface irregularities and protect the roadway from water intrusion and UV degradation. Slurry seals are used in lieu of chip seals within residential neighborhoods given the public’s general dislike of chip seals and a chip seal’s lower effectiveness in areas without high traffic volumes to press in the chips. Cape seals are used on higher volume roadways or those with heavier degradation and include a chip seal first, followed by a slurry seal several weeks later.
Rebuilds are used when the existing pavement has deteriorated to a level that is cost-prohibitive to repair and requires removal and replacement of the existing pavement. Rebuild sections will often include the repair or replacement of damaged concrete. In some instances, rebuilds will also include the installation of new sidewalks and ADA curb ramps, where appropriate. Overlays are limited to areas where the pavement and adjacent concrete may be showing signs of fatigue but are still maintainable. Overlays typically include milling the existing pavement surface to accommodate a new layer of asphalt and remove any surface irregularities.